Mining News Pro - The Pumpkin Hollow underground mine, in the US, is experiencing delays, Toronto-listed Nevada Copper reported on Friday, stating that steady state production of 5 000 t/d of ore would be deferred from mid-year to the third quarter.
The company said mechanical issues and other incidents in the main shafts had led to the delays, which resulted in lower-than-expected ore production in 2021.
Average hoisting rates for February to date were about 1 600 t/d, compared with the planned 3 000 t/d.
Nevada Copper state that retrofitting work to resolve these issues would be completed in the coming weeks.
“As a result of the shaft delays, and delayed upgrade of the underground electrical and ventilation systems, production of copper concentrates during the first half of 2021 is expected to be significantly lower than planned,” the miner said.
Milling throughput, however, performed well at an average of about 3 100 t/d in 2021, with a peak of 4 000 t/d.
“We are pleased with the continued improvements of the milling operations and the peak hoisting numbers achieved this month,” stated Nevada Copper CEO Mike Ciricillo.
“We look forward to completing upgrades to the main shaft in the coming weeks and the resulting increases in hoisting and production.”
The 5 000 t/d underground mine will produce about 60-million pounds of copper in the first five years of operations, as well as 9 000 oz of gold and 173 000 oz of silver.
Over the underground project’s 13.5-year mine life, it will average 50-million pounds of copper a year, 8 000 oz/y of gold and 15 000 oz/y of silver.
Short Link:
https://www.miningnews.ir/En/News/611535
Top copper producer Codelco reported a decline in quarterly output due to lower quality ore at its aging Chilean mines — ...
When former boss Mark Cutifani left Anglo American Plc in mid-April 2022, things had rarely looked better for the ...
Chile President Gabriel Boric said on Thursday he is targeting an increase in the country’s annual copper output by 1 ...
Brazilian miner Vale SA sees no impact from BHP Group’s bid for Anglo American on the latter’s Minas-Rio project, its ...
Copper miner Antofagasta Plc is holding meetings with investors this week for its first dollar bond offering in nearly ...
Copper needs to reach $12,000 a ton — a 20% jump from this week’s high — to incentivize large-scale investments in new ...
Teck Resources, Canada’s largest diversified miner, saw its copper production jump by 74% in the first three months of ...
Aurubis AG, Europe’s largest refined copper producer, has started a project in its Bulgarian smelter which will expand ...
Anglo American Plc said it is has received an unsolicited non-binding combination proposal from BHP Group.
No comments have been posted yet ...