Tuesday, March 24, 2020 - 12:39:43 PM
-
629 Visit
-
Print
Mining News Pro - Bacanora continues to progress all its workstreams at the Sonora project in Mexico, the lithium exploration and development company announced Monday.
According to Mining News Pro - However, the timetable for project engineering work has been impacted by delays in Asia and North America, the company said, due to the ongoing government restrictions in response to the covid-19 outbreak. As a result, completion of the project is now scheduled for Q3 2020.
Ganfeng Lithium will provide Bacanora with an engineering, procurement and construction-style engineering proposal to produce downstream battery-grade lithium products from the Sonora lithium plant.
Ganfeng, like all Chinese companies, was severely impacted by the travel restrictions imposed by the Chinese government during February and early March. Although these restrictions are now being lifted, the return to work has been slow, Bacanora noted.
Ganfeng’s main lithium processing plant at Xinyu is resuming operations and lithium production is building up. The Ganfeng test plant and project team have also resumed work on the Sonora flow sheet optimization and process engineering, and while some weeks of engineering have been lost, completion of engineering and equipment selection is now scheduled for the third quarter.
Bacanora emphasized that this schedule remains under regular review in relation to the ongoing Covid-19 situation.
Short Link:
https://www.miningnews.ir/En/News/506024
Chinese carmaker BYD Co has postponed plans to produce lithium cathodes for electric vehicle (EV) batteries in Chile by ...
Australian-based Atlantic Lithium Ltd., which is developing Ghana’s first lithium mine, has taken a step toward raising ...
Truck drivers in Chile staged protests Monday in the mineral-rich north of the country and around the capital Santiago, ...
Canada’s mining industry is pushing for an carveout to the federal government’s proposed increase to capital gains ...
London-based Savannah Resources will if necessary ask Portugal’s government to authorize compulsory land acquisitions ...
India is considering offering incentives to encourage private companies to set up lithium processing facilities, as New ...
London-based Savannah Resources will if necessary ask Portugal’s government to authorize compulsory land acquisitions ...
Australia will spend A$566 million ($373 million) over the coming decade to map out resource deposits with a focus on ...
Equinor on Wednesday said it has entered an agreement with Standard Lithium to acquire a 45% stake in lithium projects ...
No comments have been posted yet ...