Mining News Pro - Equinox Gold reports that the new primary jaw crusher at its Aurizona Gold Mine in Brazil has been energised and dry tested with the expectation of putting first ore through the system in early January 2019.
According to Mining News Pro - The ROM ore is trucked from the open pits and dumped directly into the ROM surge bin with 700 mm spacing bars, or stockpiled on the ROM storage pad and then reclaimed by a FEL to the surge bin. Any ore coarser than 700 mm is broken down by a mobile breaker. The ore in the surge bin is reclaimed by the 1,500 mm wide by 9 m long apron feeder. The ROM ore is fed onto the vibrating grizzly feeder, where the screen oversize coarser than 115 mm is directed to the jaw crusher, which crushes the screen oversize to a P80 of approximately 150 mm. The crushed ore reports to the surge bin feed conveyor which also receives the vibrating screen undersize. The combined crushed ore and the screen undersize will be conveyed to the SAG mill feed surge bin.
Project update summary:
Crusher circuit including vibrating feeder has been energised and dry tested
Commissioning team ramping up and training programs are underway
Engineering and procurement activities are complete
Tailings storage facility is complete
Powerline sub-station upgrades are complete and awaiting final verification by the state utility
Ancillary buildings and facilities are complete
At the end of November, processing plant construction was 90% complete
Concrete work is complete
Structural steel erection is 96% complete
Equipment and plate work installation is 86% complete
Piping is 76% complete
Electrical and instrumentation is 50% complete
Pre-production mining is nearing completion
More than 6.4 Mt of material moved
730,000 t of ore stockpiled and ready for commissioning
The construction team is focused on piping, electrical and instrumentation. The main transmission line is ready to provide full energization to all equipment, and site-wide distribution circuits to local electrical rooms are being commissioned to enable testing of individual equipment components.
Equinox Gold commenced full-scale construction at Aurizona in January 2018 and pre-production mining in April 2018. Approximately $116 million was spent at the end of November 30, 2018, including fiscal 2017 spending related to construction activities. The project remains fully funded. In addition to existing cash reserves, the company has $10 million remaining to draw against its $85 million construction credit facility.
Short Link:
https://www.miningnews.ir/En/News/319215
China’s Zhaojin Mining Industry said on Wednesday that its A$733 million ($477.8 million) offer to buy Australia’s ...
Toronto-listed miner OceanaGold Corp said on Wednesday it will raise 6.08 billion pesos ($106 million) through an ...
Gold’s record-setting rally this year has puzzled market watchers as bullion has roared higher despite headwinds that ...
AbraSilver Resource said on Monday it has received investments from both Kinross Gold and Central Puerto, Argentina’s ...
Gold took a tumble as haven demand waned after geopolitical tensions eased in the Middle East.
The four largest indigenous communities in Chile’s Atacama salt flat suspended dialogue with state-run copper giant ...
A prefeasibility study for Predictive Discovery’s (ASX: PDI) Bankan gold project in Guinea gives it a net present value ...
Representatives from the Peñas Negras Indigenous community, in northwestern Argentina, clashed with heavily armed police ...
Newmont confirmed on Wednesday that two members of its workforce died this week at the Cerro Negro mine located in the ...
No comments have been posted yet ...