Mining News Pro - Nicaragua-focused Condor Gold (LON:CNR) has obtained an extension to meet conditions associated with the environmental permit to build and operate its flagship La India open pit gold mine, in the country’s western region.
The company, which received the licence in August 2018, was given a time frame to meet certain conditions. Such requirements, including reaching a deal with landowners to buy their properties, must be settled before construction of the 2,800 tonnes of ore per day gold mine can begin within 18 months of the grant.
Condor said last month that it wouldn’t be able to complete the land acquisition for its mine site infrastructure in time.
The extension, granted by the Ministry of Environment and Natural Resource (MARENA), will also help the gold miner complete technical engineering tests and other studies required prior to construction.
La India is a 313 km² concession package covering 98% of the historic La India Gold Mining District. Mineral resources are 9.85 million tonnes at 3.6 grams per tonne of gold for 1.14 million indicated ounces.
The asset also has a total underground resource of 1.27 million tonnes at a grade of 5.8g/t gold for 238,000 gold ounces in the indicated category and 5.47 million tonnes at a grade of 5.1g/t gold for 889,000 ounces of gold in the inferred category.
Condor Gold is currently advancing the permitting process for two high-grade satellite feeder pits that could increase La India’s production by 50% to 120,000 ounces a year.
The America and Mestiza pits are located about 2km and 4km, respectively, from the mine’s processing plant and complement the main open pit.
The plan is to begin by mining the “mini pits” within the larger, permitted pit and transfer that ore to a nearby processing plant, chief executive officer Mark Child told MINING.COM earlier this year.
The company expects to complete the two environmental impact assessments in the second half of the year.
Condor Gold initially staked concessions in Nicaragua, Central America’s largest country, in 2006. Since then, mining has significantly taken off in the country due to the arrival of foreign companies with the cash and knowledge to tap into its reserves.
Short Link:
https://www.miningnews.ir/En/News/402312
Base metals declined after the Federal Reserve pushed back on interest-rate cut expectations and as investors weighed ...
Mining News Pro - Australia expanded its list of critical minerals deemed crucial to its energy transition and national ...
Mining News Pro - China exported small amounts of two minerals crucial to high-tech manufacturing in October, marking a ...
Mining News Pro - Townsville is set to become home to Australia’s first critical minerals processing centre, the ...
Mining News Pro - Mexico’s President Andrés Manuel López Obrador exhorted Vulcan Materials’ subsidiary, Calica, to ...
Mining News Pro - China’s exports of germanium and gallium products in August plunged, customs data showed on Wednesday, ...
Mining News Pro - The Pentagon plans to issue a first-time contract to US or Canadian companies by year-end to recover ...
Mining News Pro - When China’s Vital Materials Co. bought up a $600 million stockpile of obscure critical minerals in ...
Mining News Pro - Major miner Rio Tinto will invest $40.4 million in Sovereign Metals to advance the Kasiya ...
No comments have been posted yet ...